Time & Work
Learning Objectives
- Understand the fundamental concepts of Time & Work
- Apply key formulas and techniques to solve problems
- Practice with exam-level questions to build speed and accuracy
Foundations of Time and Work
1.1 The Unitary Principle and the Concept of Total Work
The study of time and work rests on the simple observation that the amount of work completed is the product of the rate at which a worker or a machine operates and the duration for which it operates. In quantitative aptitude, the total work is conventionally taken as one whole unit, so that a person who finishes a job in n days contributes a daily fraction of 1/n of the whole. This fractional representation makes it possible to add the contributions of several agents working together, because the sum of their daily fractions equals the combined daily fraction. When the combined daily fraction is known, the total time required is simply the reciprocal of that fraction. The unitary method therefore converts a problem about days into a problem about fractions, which can be manipulated with ordinary arithmetic.
1.2 Choosing a Convenient Measure of Work: The LCM Technique
Although the fractional approach is mathematically sound, it often leads to cumbersome denominators when several workers with different individual times are involved. A widely adopted shortcut is to assume the total work to be the least common multiple (LCM) of all the given individual times. If A completes a task in 12 days and B in 18 days, the LCM of 12 and 18 is 36. Treating the whole job as 36 units of work turns A’s daily output into 3 units per day and B’s into 2 units per day. The combined daily output becomes 5 units, and the required time is 36 ÷ 5 = 7.2 days. This technique eliminates fractions entirely, reduces the chance of arithmetic error, and makes mental calculation feasible under examination pressure.
1.3 Inverse Relationship Between Time and Efficiency
Efficiency is defined as the amount of work done per unit time. Because the total work is fixed, a worker who needs fewer days to finish the same job must have a higher daily output; consequently, efficiency is inversely proportional to the time taken. If A finishes a task in half the time required by B, A’s efficiency is exactly twice that of B. This inverse proportionality allows us to replace statements such as “A is thrice as efficient as B” with the equivalent time ratio “A takes one‑third the time of B”. In combined‑work problems, the efficiencies of all participants are simply added, because each contributes independently to the total work done each day. The sum of efficiencies, expressed either as fractions of the whole or as LCM‑based units, gives the combined daily progress.
Efficiency and Combined Work
2.1 Adding Efficiencies When Workers Operate Simultaneously
When two or more persons work together from the start, their individual daily contributions accumulate without interference. If the total work is taken as the LCM of their individual times, each person’s efficiency becomes an integer number of work units per day. The combined efficiency is the arithmetic sum of these integers. The total time required is then the total work divided by the combined efficiency. This method works regardless of whether the workers have equal or unequal efficiencies, and it extends naturally to any number of participants. The key point is that simultaneous work implies a simple additive model for daily output.
2.2 Partial Participation and the Concept of Work Done Before Joining or Leaving
In many examination questions, a worker may start later, leave early, or work only for a specified number of days. The total work is still the LCM of all relevant times, but the contribution of each worker must be weighted by the actual number of days he or she works. For instance, if A works for 4 days and B works for the entire duration, A’s contribution is 4 × (efficiency of A) while B’s contribution is (total days) × (efficiency of B). The equation “sum of weighted contributions = total work” yields the unknown total days. This approach also handles situations where a worker’s efficiency changes midway, because the work can be split into phases, each with its own combined efficiency.
2.3 Efficiency Ratios Derived from Statements Like “A Is Twice As Good As B”
Verbal descriptions of relative efficiency are common in competitive tests. The phrase “A is twice as good as B” means that in the same time A completes twice the work of B, or equivalently A needs half the time of B for the same job. Translating such statements into numerical ratios is straightforward: if the efficiency ratio A : B = 2 : 1, then the time ratio A : B = 1 : 2. When three or more workers are compared, a chain of ratios can be built and then reduced to a common base, after which the LCM method can be applied. Mastery of this translation eliminates the need to set up algebraic equations for every comparative statement.
Pipes and Cisterns
3.1 Modelling Inlet and Outlet Pipes as Positive and Negative Efficiencies
A pipe that fills a tank performs positive work, exactly analogous to a worker adding to the completed portion of a job. Conversely, a drain or outlet pipe removes water, which is negative work. If an inlet pipe can fill the tank in a hours, its hourly rate is +1/a of the tank. If an outlet pipe can empty the tank in b hours, its hourly rate is –1/b. When several pipes operate together, the net hourly rate is the algebraic sum of all individual rates. The time to fill (or empty) the tank is the reciprocal of the net rate, provided the net rate is positive for filling and negative for emptying. This direct translation of the work‑rate framework to pipes makes the topic a mere variation of the combined‑work model.
3.2 Using the LCM of Pipe Times to Avoid Fractions
Just as with human workers, the LCM of all given filling and emptying times can be taken as the tank’s capacity in arbitrary units. An inlet pipe that fills in 8 hours contributes LCM/8 units per hour; an outlet that empties in 6 hours contributes –LCM/6 units per hour. The net hourly contribution is the sum of these signed integers. The required time is then the capacity divided by the net hourly contribution. This integer‑based method is especially valuable when three or more pipes are involved, because it sidesteps the need to find a common denominator for several fractions.
3.3 Situations Where the Tank Is Partially Filled or Multiple Phases Occur
Examination questions often introduce a twist: the tank may already contain some water, or pipes may be opened and closed in stages. In such cases the problem is split into phases. For each phase, identify which pipes are active, compute the net rate for that phase using the LCM method, and determine how much the water level changes during the phase’s duration. The final answer is obtained by adding the durations of all phases until the tank reaches the desired level (full or empty). The phase‑wise approach mirrors the partial‑participation technique used for workers who join or leave.
| Aspect | Fractional Method | LCM Method |
|---|---|---|
| Representation of rates | Fractions such as 1/8, –1/6 | Integers such as 3, –4 (when LCM = 24) |
| Arithmetic complexity | Requires common denominator for addition | Simple integer addition and subtraction |
| Error proneness | Higher, especially with three or more pipes | Lower, because only whole numbers are handled |
| Speed under exam conditions | Moderate | Fast once LCM is identified |
Alternate Day Work and Interruptions
4.1 The Two‑Day Cycle Concept for Strict Alternation
When two workers operate on alternate days, the pattern of work repeats every two days. If A works on day 1, B on day 2, A on day 3, and so on, the combined work done in each two‑day cycle is the sum of A’s one‑day work and B’s one‑day work. By expressing each person’s one‑day work as a fraction of the total (or as LCM units), the work completed per cycle becomes a fixed quantity. The number of full cycles needed is the integer part of (total work ÷ work per cycle). The remainder after the last full cycle is then handled by simulating the next day(s) in the correct order until the work is finished. This cycle‑based reasoning avoids day‑by‑day simulation for large numbers of days.
4.2 Handling a Starter Other Than the First Worker
The problem statement may specify that B starts instead of A, or that the alternation begins after a certain number of days of solo work. In every case the first step is to determine the exact sequence of workers for the first few days, compute the work done in that initial segment, and then apply the regular two‑day cycle to the remaining work. The order of workers in the cycle is crucial because the remainder may be completed by the first worker of the next cycle, the second worker, or may require a partial day from the second worker. Writing down the first three or four days explicitly eliminates ambiguity.
4.3 Interruptions Such as Rest Days or Efficiency Drops
Some questions introduce a rest day after a fixed number of working days, or a sudden change in a worker’s efficiency (for example, due to fatigue). The solution strategy remains phase‑wise: treat each uninterrupted block as a separate combined‑work problem with its own set of active workers and efficiencies. Compute the work finished in each block, subtract from the total, and continue with the next block. Because the LCM method works with integer units, the transition between blocks is seamless — the remaining work is simply the original total minus the sum of work done in all previous blocks.
| Starting Worker | Work Done in First Two Days (units) | Typical Remainder Handling |
|---|---|---|
| A (efficiency 3) then B (efficiency 2) | 5 | Remainder ≤ 3 → finished by A on next day; 3 < remainder ≤ 5 → finished by B on following day |
| B (efficiency 2) then A (efficiency 3) | 5 | Remainder ≤ 2 → finished by B on next day; 2 < remainder ≤ 5 → finished by A on following day |
Wages and Distribution of Earnings
5.1 The Principle of Proportional Division Based on Work Done
When a group of workers completes a job for a fixed total wage, the fair division of that wage is in direct proportion to the amount of work each person actually performed. Since work done equals efficiency multiplied by the number of days worked, the share of each worker is (efficiency × days worked) divided by the sum of such products for all workers, multiplied by the total wage. This rule holds whether the workers labour simultaneously, sequentially, or in any mixed schedule. The underlying assumption is that the wage compensates for the contribution to the finished product, not merely for the time spent on site.
5.2 Applying the LCM Framework to Wage Problems
Using the LCM of individual times as the total work converts each worker’s efficiency into an integer number of units per day. The work contributed by a worker then becomes an integer (efficiency × days). The ratio of these integers is exactly the ratio of their wage shares. For example, if total work = 60 units, A’s efficiency = 3 units/day, B’s = 2 units/day, and A works 4 days while B works 6 days, A contributes 12 units and B contributes 12 units. The wage is split equally because the contributions are equal, even though their efficiencies differ. This integer‑based ratio method eliminates fractions and makes the division transparent.
5.3 Scenarios Involving Partial Payment, Penalties, or Bonus Conditions
Advanced questions may state that a worker receives a fixed daily wage plus a bonus for early completion, or that a penalty is deducted for each day of delay. In such cases the base wage is first divided according to work done, and then the additional terms are applied individually. If a bonus is shared in the same proportion as the base wage, the bonus amount is simply distributed using the same work‑ratio. Penalties that depend on the overall project duration affect all workers equally only if the contract specifies a collective penalty; otherwise each worker’s penalty is linked to his own attendance. Careful reading of the wording determines whether the extra amount is pooled before division or allocated per person.
Mastering these five thematic areas — foundations, efficiency, pipes, alternate‑day patterns, and wages — equips a candidate to solve every standard time‑and‑work question that appears in the quantitative aptitude section of banking examinations.
Pairwise Combined Efficiencies and the Three‑Worker System
When a problem gives the time taken by three workers A, B and C in pairs — A and B together finish in x days, B and C in y days, C and A in z days — the individual efficiencies can be recovered without solving a system of three equations. Let the total work be the LCM of x, y, z (or any convenient multiple). The combined efficiency of A and B is W/x units per day, of B and C is W/y, of C and A is W/z. Adding the three pairwise efficiencies gives twice the sum of individual efficiencies: 2(EA+EB+EC) = W(1/x+1/y+1/z). Hence the combined efficiency of all three is half of that sum. Individual efficiencies follow by subtraction: EA = (EA+EB+EC) – (EB+EC), and similarly for B and C. This shortcut eliminates fractions and works even when the pairwise times are not co‑prime.
Extension to Four Workers
For four workers the same principle extends: given the six pairwise combined times, the sum of all six pairwise efficiencies equals three times the sum of the four individual efficiencies. The factor changes from 2 to 3 because each worker appears in exactly three pairs. The combined efficiency of all four is one‑third of the sum of the six pairwise efficiencies. Individual efficiencies are then obtained by subtracting the appropriate three‑pair sums. The method scales to any number of workers provided all pairwise data are available.
When Only Some Pairs Are Known
If the problem supplies only two pairwise times and the time taken by all three together, the third pairwise time can be derived. Let the three‑worker combined time be t. Using the relation 2(EA+EB+EC) = sum of pairwise efficiencies, and knowing EA+EB+EC = W/t, we get the missing pairwise efficiency = 2W/t – (known pairwise efficiencies). This algebraic inversion is a commonly tested pattern.
Man‑Day Equivalence and Mixed Workforce Problems
The concept of man‑days (or person‑days) treats work as the product of the number of workers and the number of days they work, assuming uniform efficiency. When workers of different categories — men, women, children, or machines — have different efficiencies, the equivalence is established by expressing each category in terms of a base unit. For example, if 1 man = 2 women = 3 children in efficiency, then 1 man‑day = 2 woman‑days = 3 child‑days. The total work in base units is the sum over all categories of (number of workers × days × efficiency factor). This converts a heterogeneous workforce into a single homogeneous measure, allowing the standard LCM or unitary method to be applied.
Changing Composition Mid‑Project
A common variant adds or removes workers after a certain number of days. The work done in the first phase is computed with the initial composition; the remaining work is then tackled with the new composition. Because the base‑unit work is additive, the remaining work in base units is simply total base units minus work done in phase one. The time for phase two equals remaining base units divided by the new combined efficiency in base units per day. If the change occurs at a fractional day, the same arithmetic holds — compute work done up to the exact moment of change using the efficiencies active at that moment.
Multiple Shifts and Overlapping Teams
When two teams work in overlapping shifts (e.g., Team A works 8 am–4 pm, Team B works 12 pm–8 pm), the overlapping period has the sum of both teams’ efficiencies, while the non‑overlapping periods have only one team’s efficiency. The day can be split into intervals with constant combined efficiency. The total work per day is the sum over intervals of (interval length × combined efficiency). This interval method avoids the error of averaging efficiencies across the whole day.
Variable Efficiency and Learning‑Curve Scenarios
Some problems state that a worker’s efficiency changes after a certain amount of work is done or after a fixed number of days — for instance, “A’s efficiency drops by 20 % after 5 days” or “B becomes twice as fast after completing half the work”. The solution is to split the project into phases where efficiency is constant. In each phase, compute the work done using the efficiency applicable to that phase. The transition point is either a day count or a work‑quantity threshold. If the trigger is a work quantity (e.g., half the work), first determine how many days the first phase lasts by dividing the trigger work by the initial efficiency. Then apply the new efficiency for the remaining work. Because the LCM method works with integer units, the trigger work can be expressed in the same units, keeping all arithmetic integral.
Gradual Efficiency Change
When efficiency changes gradually (e.g., “A’s efficiency increases by 1 unit per day”), the work done each day forms an arithmetic progression. The total work over n days is the sum of the progression: n/2 × (2a + (n‑1)d), where a is the first day’s efficiency and d the daily increment. Equate this sum to the total work (in LCM units) and solve the resulting quadratic for n. The quadratic typically yields an integer root in exam questions. If the root is not an integer, the last day is a partial day; compute the exact fraction by subtracting the work done in full days from the total and dividing by the efficiency on the next day.
Efficiency Drop Due to Fatigue
A fatigue model may state “after every 3 days of work, A rests for 1 day”. This is a periodic pattern, not a one‑time change. Treat each 4‑day block as a cycle: 3 working days at efficiency e, 1 rest day at efficiency 0. The work per cycle = 3e. Number of full cycles = floor(total work / 3e). Remainder work is handled by simulating the next working days in order. This cycle approach is identical to the alternate‑day cycle but with a longer period and a zero‑efficiency day included.
Multi‑Phase Pipe Networks with Leakage and Unknown Capacity
Advanced pipe problems introduce multiple inlets, multiple outlets, and a leak whose rate may be unknown. The standard sign convention remains: inlets positive, outlets and leaks negative. When the tank capacity is not given, assign a variable C (or use LCM of all given times as a proxy capacity). Write the net rate equation for each phase. For example, “Pipe A fills in 6 h, Pipe B fills in 8 h, Leak empties in 12 h. All three are opened together for 2 h, then the leak is plugged.” Phase 1 net rate = C/6 + C/8 – C/12 = (4C+3C–2C)/24 = 5C/24 per hour. Work in 2 h = 10C/24 = 5C/12. Remaining = 7C/12. Phase 2 net rate = C/6 + C/8 = 7C/24. Time for phase 2 = (7C/12) ÷ (7C/24) = 2 h. Total = 4 h. The capacity C cancels, confirming that the answer is independent of the actual volume.
Leak Rate Determined by Observation
If the leak rate is not given directly but the tank fills in a known time with all pipes open, the leak rate can be back‑calculated. Let the combined inlet rate be Rin and the observed fill time be T. Then net rate = C/T = Rin – Rleak. Hence Rleak = Rin – C/T. Once Rleak is known, any subsequent phase (e.g., leak plugged, or additional outlet opened) can be solved with the same sign convention.
Sequential Opening and Closing
When pipes are opened or closed at different times, break the timeline into intervals where the set of active pipes is constant. For each interval, compute the net rate using the active pipes’ efficiencies. Multiply by interval length to get work done. Sum across intervals equals total capacity. This interval method is identical to the overlapping‑shift technique for workers and avoids the common mistake of averaging rates over the whole duration.
Wage Distribution with Differential Rates and Penalty Clauses
Beyond simple proportional division, wages may be paid at different rates per unit of work for different workers, or a penalty may be levied on the whole group for delay. If worker A earns ₹p per unit and worker B earns ₹q per unit, the total wage = p × (work by A) + q × (work by B). The work by each is still efficiency × days. The ratio of their shares is p·EA·dA : q·EB·dB. This reduces to the standard ratio when p = q. When a penalty of ₹P is deducted for each day beyond the deadline, first compute the actual completion day. If the deadline is D days and the work finishes on day F > D, the total penalty = P × (F – D). The contract may specify that the penalty is shared in the same proportion as the base wage, or that each worker bears a penalty proportional to his own days of work. Read the wording: “penalty is shared equally” means divide P×(F–D) by number of workers; “penalty is deducted from each worker’s share in proportion to his work” means multiply each worker’s base share by (1 – penalty fraction).
Bonus for Early Completion
A bonus ₹B for finishing before the deadline is added to the total pool before division if the statement says “the bonus is distributed among the workers in the ratio of their work”. In that case, total distributable amount = base wage + B. Each worker’s share = (his work / total work) × (base wage + B). If the bonus is a fixed amount per worker (e.g., “each worker receives ₹500 bonus”), simply add that amount to each individual’s calculated share after the base division.
Partial Payment and Advance
When a worker receives an advance before the work starts, the advance is deducted from his final share. Compute the final share as per the work ratio, then subtract the advance. If the advance exceeds the final share, the worker owes the difference — a situation that sometimes appears as “find the amount to be recovered”. The arithmetic remains the same; only the sign of the final settlement changes.
- Assuming pairwise times can be averaged instead of using the 2× sum rule.
- Forgetting to convert mixed workforce into a common base unit before applying LCM.
- Treating a gradual efficiency change as a single average efficiency rather than summing an arithmetic progression.
- Ignoring the sign convention for leaks and outlets, leading to net rates that are too high.
- Applying a penalty or bonus to the wrong pool (base wage vs. total distributable amount).
- Misreading “shared equally” versus “shared in proportion to work” for penalties and bonuses.
- Overlooking that an advance payment must be subtracted from the final calculated share, not added.